Construction Of Grade Separators And Vehicular Underpass With RE Wall Approaches On Both Sides
Client: NHAI (As Approved Sub-Contracter)
PMC: STUP CONSULTANT (P) LTD.,
Contract Value: 140 Millions
Contract Period: 9 Months
Salient Features
Construction Of Flyover With RE Wall Approaches
Client: NHAI
PMC: JASTOLL ROAD COMPANY LTD.,CES CONSULTANCY
Contract Value: 225 Millions
Contract Period: Nov.2002-Dec.2003
Salient Features
235 Mt Long River Bridge On North Cauvry
Client: Soma Enterprises Ltd., for KRDCL
PMC: CES CONSULTANCY
Contract Value: 32 Millions.(Excluding Concrete & Steel)
Contract Period: 9 Months.
Salient Features: 33 Mts PSC ‘I’ Girders of 7 Spans 3 Lane Bridge on North Cauvery River.
160 Mt Long River Bridge On South Cauvry At Sriranga Patna
Client: Soma Enterprises Ltd., for KRDCL
PMC: CES CONSULTANCY
Contract Value: 32 Millions.(Excluding Concrete & Steel)
Contract Period: 9 Months.
Salient Features: 40 Mts. PSC Box Girders of 4 Spans 3 Lane Bridge on South Cauvery River 160 mts long River Bridge at Sri Ranga Patna on South Cauvery - SH 17 13
Construction Of Road Over Bridge
Client: South Western Railway
Contract Value: 1200 Millions
Salient Features: About 600 meters long ROB of 12 spans (each 26 meters ) with R.E. Wall Approaches. (Width of couriage way is 14 meters)
88 Nos of 26 mts. P.S.C. Girders and 8 Nos of 30 mts. P.S.C. Girders for Railway Span.
Construction Of Road Over Bridge
Client: South Western Railway
Contract Value: 1100 Millions
Salient Features: About 850 meters long ROB of 4 spans (each 36.5 meters) with R.E. Wall Approaches (max. hight of 12 meters) about 8,500 sqm
20 Nos. of 36.5 P.S.C. Girders
Construction Of Road Over Bridge At Km 0+270 NH-7 Including Approaches, Under Pass And Culvert
Client: IRCON INTERNATIONAL LIMITED
Contract Value: 1530 Millions
Salient Features: P.S.C. Bridge along with approaches of about 1500 mts. length with R.E. Wall approches, earthen embankments and under passes etc.,
Construction Of Road Over Bridge At Km 0+270 NH-7 Including Approaches, Under Pass And Culvert
Client: IRCON INTERNATIONAL LIMITED
Contract Value: 2012 Millions
Salient Features: About 1400 mts. long 3 spans (each 37 meters) with R.E. Wall Approaches and earthen embankments with under passes etc.,
Construction Of Road Over Bridge At Km 0+270 NH-7 Including Approaches, Under Pass And Culvert
Client: IRCON INTERNATIONAL LIMITED
Contract Value: 1640 Millions
Salient Features: P.S.C. Bridge along with approaches of about 1500 mts. length with R.E. Wall approches, earthen embankments and under passes etc.,
Construction Of R.O.B. In Lieu Of L.C. No. 315 ‘A’ & ‘B’ At Nainavaram Gate, Vijayawada
Client: SOUTH CENTRAL RAILWAY
Contract Value: 3400 Millions
Salient Features: Bridge with pile foundation, R.C.C. Columns, and Superstructure as 1 x 36 mtrs. + 5 x 32 mtrs. + 2 x 21 mtrs. + 1 x 16 mtrs etc., span PSC box girders and R.C.C. T-Beam. Trestle structure over pile foundation for the span of 22.5 mtrs. for 20 spans.
Construction Of Road Over Bridge For South Central Railwayat Dwarapudi, East Godavari District
Client: SOUTH CENTRAL RAILWAY
Contract Value: 441 Millions
Salient Features: Proposed Construction of Road Over Bridge with pile foundations, RCC Columns and super structure with clear span composite girder (ie., steel ‘I’ Girders with RCC deck slab).
Construction Of Major Briges For South Western Railway At Kolar, Bangalore
Client: SOUTH WESTERN RAILWAY
Contract Value: 1811 Millions
Salient Features: Proposed construction of 6 nos Major Briges, Road under bridges and regarding of approaches roads between kolar - chintamani section
Improvements To Storm Water Drains For Greater Visakhapatnam Municipal Corporation, Visakhapatnam
Client:Greater Visakhapatnam Municipal Corporation
Contract Value: 3926 & 1213 millions
Salient Features: Improvements to storm water drains of Greater Visakhapatnam city
Construction of Approaches to the Fly Over at Vijayawada
Client: Andhra Pradesh Capital Region Development Authority
Contract Value: 31.48 crores
Salient Features: Preparation of Estimates, Designs and Drawings, Pile Foundations, RCC Sub Structure and PSC Super Structure of (28.00m spans 28 nos. and 29.00m spans 4 nos.) 450 mts length of four lane bridges, 319.50 mts length of Four Lane RE wall approach roads and 693.50 mts length of four lane Road.
Earth work in formation construction of minor bridges and RUB from Ch: 30950 m to Ch. 38975 m between Mattampalli and Janpahad stations
Client: South Central Railway
Contract Value: 46.49 cr
Salient Features: Earth work excavation for foundations of Bridges and in formation, earthwork in embankment, Construction of minor bridges, road under bridges and other connected works.
Construction of four laned ROB at KM. 76.380 of Nagpur - Hyderabad section of NH-07 at Hinganghat, Maharashtra
Client: National Highways Authority of India
Contract Value: 35.00 cr
Salient Features: Construction of four laned ROB Pile Foundation & Open Foundation, RCC Sub-Structure, PSC Super Structure (8 Spans of 14.100 m. PSC I Girders ) and Composite Steel Girder on Railway Span (2 Spans of 30.383 m. Composite Steel Girders ) with RE Wall Approaches and Road works like Sub Grade, GSB, WMM, DBM, BC and Mastic Asphalt etc.
Kolar - Chikkaballapur gauge conversion from NG to BG Proposed construction of Manor Bridges between Kolar and Chintamani section
Client: South Western Railway
Contract Value: 18.87 cr
Salient Features: Major bridges work with pile and open foundations, RCC Sub structure, PSC I girders, RCC deck slab, Earthwork in excavation and embankment & protective works.
Construction of ROB with approaches at Birur station, Karnataka
Client: Karnataka State highways Improvement Project, Bangalore
Contract Value: 38.87 cr
Salient Features: Construction of ROB RCC Foundation, RCC Sub-Structure, RCC Super Structure (2 Spans of 18.100 m) and Composite Steel Girders (1 Span of 42.00 m.) with RE Wall Approaches and Road works like Sub Grade, GSB, WMM, DBM, BC etc.
Construction of Major Bridges at Tori - Shivpur new B.G. Rail Line, Jharkhand
Client: East Central Railway
Contract Value: 62.34 cr
Salient Features: Construction of Major Bridges Open Foundation, RCC Box Bridges of 100 mt barel length (6 mt X 6 mt size) 3 vents, 75 mt barel length (6 mt X 6 mt size) 3 vents and Composite Steel Girders (span 4 X 30.5 M) earth work in excavation and embankment & protective works etc.
Construction of Major Bridges at BRKA-RNC new B.G. Rail Line, Jharkhand
Client: East Central Railway
Contract Value: 41.30 cr
Salient Features: Construction of Major Bridges Open Foundation, Composite Steel Girders (span 14 X 30.5 M) and (span 2 X 18.3 M) earth work excavation in formation and embankment & other associated works etc.
CCONSTRUCTION OF HLB ON MANAIR RIVER
Client: R & B Department, Telangana
Contract Value: 43.97 cr
Salient Features: Construction of 40 Mts span PSC Girder bridge with circular Piers with Hammer Head Bed Blocks with 3071.155 Rm Pile foundation.
Construction of Railway Officers Rest House & Railway Tickets Reservation Counter at Governorpet, Vijayawada
Client: RAIL VIKAS NIGAM LIMITED
Contract Value: 6.60 cr
Construction of half flyover, RE wall approaches, at Km.1082+320
Client: National Highways Authority of India
Contract Value: 33.98 Cr
Construction of Important Bridge on Manair River
Client: South Central Railway
Contract Value: 24.86 Cr
Salient Features: Construction of Major Bridge with Double D Well Foundation (13 mt dia), 1.20mt dia Pile Foundation and 27 X 18.3 mt i.e (Total 54 nos PSC I Girders) for Sup
Construction of Road Over Bridges At Nagpur, Maharashtra
Client:Maharashtra Rail Infrastructure Development Corporation Limited
Contract Value: 55.87 Cr
Salient Features: Construction of Road Over Bridges (ROBs) at 2 Locations LC No. 548 - km 1088/5-7 between Rewral-Tharsa Stations, LC No. 559 - km 1111/12-14 Near Kanhan Station in Maharashtra area on Nagpur Division of South East Central Railway.
Construction of Major bridges At Jogidih - Obra Dam, Uttar Pradesh
Client:East Central Railway
Contract Value: 177.98 Cr
Salient Features: Major Bridges work on water ways upto a height of 25 mt, RUBs, Supply, Fabrication and launching of Steel Girder Spans 13 X 12.2 M spans i.e (Total 158.60 mts), 14 X 18.3 M spans i.e (Total 256.20 mts), 6 X 24.4 M spans i.e (Total 146.4 mts) & 13 X 30.5 M spans i.e (Total 396.50 mts) Open Foundations, Pile Foundations, Earthwork in Cutting and Embankment for Formation, Prepared Sub Grade, Blanketing, Slope Protection Works.